Search Copa
   » Products
   » News & Events
   » Ask Our Experts
   » Related Links
   » Case Studies
   » Downloads
   » Global Distributors
  Your email    Privacy
 
to unsubscribe click here
Case studies
  » Return to previous page
 
  MBR - Longbridge Wastewater Treatment Plant  
  Printer Version
 



• Complete upgrade of existing WwTW
• Designed to treat effluent from a population of 1,471 people
• Constructed within one main treatment structure
• Designed, built and operational within 8 months
• High quality discharge parameters

Current Status: Plant operational April 2003
Client: Wessex Water Services Limited
Required Performance: 13:26:4 BOD:SS:Ammonia
Performance: <5:5:1 BOD:SS:Ammonia
Brief Description: New membrane plant to replace existing WwTW to treat increased domestic flows and the high ammonia load from a trade effluent source to comply with new Environment Agency discharge consent.

Process Description

The plant, receives pumped flows from two catchments and a gravity flow from a third area.

The influent enters an existing balancing tank and is pumped via an upgraded pumping station to an elevated inlet works. The inlet works comprises 3mm screening and grit removal. The hydraulic design of the plant then allows gravity flow through the MBR plant to the main outfall without the need for inter-stage pumping.

The MBR treatment plant has been constructed on the area of sludge drying beds from the existing works. This allowed the MBR plant to be constructed without requiring additional land area and allowed the existing works to remain operational with minimal modifications during the construction period.


The works can receive high and varying inlet ammonia concentrations. The plant has been designed to ensure that these fluctuations in concentration do not effect the discharged permeate standard.

The main membrane treatment structure, constructed in reinforced concrete, is divided into four membrane bioreactor tanks. The structure also comprises common flow split, permeate collection and sludge re-cycle tanks. This main treatment structure is 14.7m long, 7.7m wide and 4m high. To both minimise the visual appearance of the structure and to overcome ground condition issues, it is buried 2m in the ground.

Following treatment in the MBR plant, the permeate is discharged direct to the local watercourse.

Design data
Population Equivalent
Peak Flow:
Average Flow:
BOD load:
Average Nitrogen load:
Average Nitrogen Concentration:
Peak Nitrogen Concentration:


1,471
1,555 m3/day
271 m3/day
90 kg/d
14 kg/d
50 mg/l
250 mg/l

Plant data

Each Tank dimensions:
No of membrane units:
Membrane surface area:



5.3 x 3.4 x 4.0m
20 x 150 panels
2,400 m2